Jail record · Sept. 6, 2018

Bureau of Prisons memo approving camera system upgrade at MCC New York, 2018

Federal Bureau of Prisons memorandum seeking approval to exceed funding limits for an $800,000 replacement of MCC New York's failing camera system.Machine-written summary

U.S. Department of Justice Memorandum Federal Bureau of Prisons

EFTA00141789

U.S. Department of Justice Memorandum Federal Bureau of Prisons

MCC New York

150 Park Row

New York, NY 10007

September 6, 2018

FROM:

SUBJECT:Request to Exceed Work Request Funding Limitation
MWR #8158 - Replace Camera System
MCC New York

It has come to my attention that the work request referenced above will require MCC New York to exceed the $10,000.00 work request funding limitation. Therefore, I am submitting this request for approval to exceed the funding limit policy. This request is submitted in accordance with the guidelines set forth in Facilities Operations Manual, PS4200.12, Chapter 2, Page 4.

The statement of work for this project is as follows: This MWR is required to replace (2) DVRs for the NICE camera system, the encoders and decoders as well as rack mounts and power supply, the server, purchase a recorder redundancy license for 350 channels, install 272 cameras and upgrade software for said systems. The vendor will also provide 4 hours of on-site training for operators and administrators.

I certify that materials have not been ordered and construction work has not been performed on the minor work request referenced above.

Work Order Estimated Cost:$800,000
Funding by Decision Unit:E1
Estimated Staff Man-Hours:800
Estimated Start Date:December 1,2018
Estimated Completion Date:February 9,2019

EFTA00141790

All supporting documentation is attached for your reference. If you have any further questions or concerns regarding this matter, please contact me.

Attachments: SCI, IGE

EFTA00141791

2.5 - Schedule of Cost Input (SCI)

Date8/24/2018RequestInitial
InstitutionMCC NEW YORKCategoryGeneral Repairs
Project TitleReplace Camera System
Object ClassFY18FY19FY20
POSWY$ x 1000POSWY$ x 1000POSWY$ x 1000
11.1 Full-Time Permanent
11.5 Other Personal Compensation
12.1 Personal Benefits: Civilian
21.0 Travel and Transportation of Persons
22.0 Transportation of Things
23.2 Rental Payments to Others
23.3 Communication, Utilities and Miscellaneous Charges
24.0 Printing and Reproduction
25.0 Other Contract Services19767.4
26.0 Supplies and Materials32.6
31.0 Minor Equipment
32.0 Land Structures
Total800.00.00.0
Total 800.0 Total in Dollars $800,000.00
Current ConditionsCurrently, MCC New York has two ninety six (96) channel DVR's which have failed repeatedly, leaving critical areas of the institution without video coverage. There are no OEM replacement parts available for purchase to repair the recorders. The current recorders use obsolete technology which cannot be upgraded without upgrading equipment. They are unsupportable, unreliable, and have exceeded their life expectancy. Cameras and recorders are an essential component which supports a safe and secure environment for both inmates and staff.
ProposalWe propose to hire a contractor to replace two existing ninety six (96) channel DVR's with a new three hundred fifty (350) channel NVR systems configured at 4CIF, 15FPS to RAID 6 array for 14 days, provide a redundant recorder in a Plus (1) one configuration, replace the existing AMS server and Decoder, install two hundred seventy two (272) cameras, and provide four (4) hours total of on-site training for operators and administrators on the latest software package.
a. MCC New York, 150 Park Row, NY, NY
b. N/A

Page 1

Bureau of Prisons memo approving camera system upgrade at MCC New York, 2018

Jail records

Federal Bureau of Prisons memorandum seeking approval to exceed funding limits for an $800,000 replacement of MCC New York's failing camera system.

DOJ Epstein Files, Data Set 9 · Sept. 6, 2018

U.S. Department of Justice Memorandum Federal Bureau of Prisons EFTA00141789 U.S. Department of Justice Memorandum Federal Bureau of Prisons MCC New York 150 Park Row New York, NY 10007 September 6, 2018 FROM: <table border="1" <tr <td SUBJECT:</td <td Request to Exceed Work Request Funding Limitation</td </tr <tr <td </td <td MWR 8158 - Replace Camera System</td </tr <tr <td </td <td MCC New York</td </tr </table It has come to my attention that the work request referenced above will require MCC New York to exceed the $10,000.00 work request funding limitation. Therefore, I am submitting this…