Federal Bureau of Prisons¶
MR 02 Monthly B&F Project Report¶
From 7/1/2019 to 7/31/2019¶
WO #:10484¶
Region: NER¶
Month Code: 10¶
Institution: NYM¶
Project #:¶
Approval: 7/18/2019¶
| Title: | 2D3S Remove Asbestos |
| Expiration: | 7/18/2022 |
Funding¶
| ng |
|---|
| Fiscal Year Funded: 2019 |
| Percent Obligated: 0% |
| Allotted: | $100,000.00 |
| Obligated: | $0.00 |
| Unobligated: | $100,000.00 |
Construction Status¶
Completion Percentage: 01%¶
Est. Completion: 7/18/2022¶
Progress Status: On Schedule¶
Completed:¶
Staff Man Hours¶
Total B&F ManHours:¶
Total S&E ManHours: 2.00¶
B&F ManHours this Month:¶
S&E ManHours this Month: 2.00¶
Estimated Hours: 600¶
Total S&E and B&F ManHours: 2.00¶
Detail Check List¶
☐ A&E Services required.¶
New construction will result in capitalization of a building or other structure.¶
Renovation will result in capitalization of an improvement to an existing building or other structure.¶
☑ Asbestos Abatement is required or has been completed.¶
☐ ESPC or UESC funded¶
□ FITARA process is required.¶
Funding¶
| Fiscal Year Funded: | 2019 |
| Percent Obligated: | 0% |
| Allotted: | $120,320.00 |
| Obligated: | $0.00 |
| Unobligated: | $120,320.00 |
Construction Status¶
Completion Percentage: 01%¶
Est. Completion: 7/25/2022¶
Progress Status: On Schedule¶
Completed:¶
Staff Man Hours¶
Total B&F ManHours:¶
Total S&E ManHours: 1.00¶
Total S&E and B&F ManHours: 1.00¶
| B&F ManHours this Month: |
| S&E ManHours this Month: 1.00 |
| Estimated Hours: |
Detail Check List¶
☐ A&E Services required.¶
New construction will result in capitalization of a building or other structure.¶
Renovation will result in capitalization of an improvement to an existing building or other structure.¶
☐ Asbestos Abatement is required or has been completed.¶
☐ ESPC or UESC funded¶
□ FITARA process is required.¶
Significant Project Events / Project Delays (Current Month Only)¶
2D3U Replace PBX - Project Approval Received 7/25/19. Procurement Documents Initiated.¶
AW:¶
Page 1 of 9¶
EFTA00142424¶
Federal Bureau of Prisons¶
MR 02 Monthly B&F Project Report¶
From 7/1/2019 to 7/31/2019¶
WO #:6633¶
Region: NER¶
Month Code: 10¶
Institution: NYM¶
Project #: 2C4G¶
Title: 2C4G Replace Doors Phase 2¶
Approval: 6/7/2017¶
Expiration: 6/7/2020¶
Funding¶
| Fiscal Year Funded: | 2017 |
| Percent Obligated: | 96.3219% |
| Allotted: | $116,746.48 |
| Obligated: | $112,452.48 |
| Unobligated: | $4,294.00 |
Construction Status¶
Completion Percentage: 61%¶
Est. Completion: 6/7/2020¶
Progress Status: On Schedule¶
Completed:¶
Staff Man Hours¶
Total B&F ManHours:¶
Total S&E ManHours: 254.00¶
Total S&E and B&F ManHours: 254.00¶
B&F ManHours this Month:¶
S&E ManHours this Month: 1.00¶
Estimated Hours: 3,705¶
Detail Check List¶
☐ A&E Services required.¶
New construction will result in capitalization of a building or other structure.¶
☑ Renovation will result in capitalization of an improvement to an existing building or other structure.¶
☐ Asbestos Abatement is required or has been completed.¶
☐ ESPC or UESC funded¶
☐ FITARA process is required.¶
Significant Project Events / Project Delays (Current Month Only)¶
2C4G Replace Doors Housing Unit Phase II -¶
Number of Doors Installed This Month - 0¶
The Doors Were Installed On Unit -¶
Staff Hours Used This Month - 0¶
Cost of Materials Used This Month - $0¶
Number of Doors Left to Install On This Project - 14¶
Facility Manager:¶
AW:¶
Page 2 of 9¶