Record · July 2019

Bureau of Prisons monthly facilities project report for NYM, July 2019

Bureau of Prisons monthly building and facilities report for the NYM institution covering July 2019, detailing construction project funding, asbestos abatement, and door replacement progressMachine-written summary

Federal Bureau of Prisons

MR 02 Monthly B&F Project Report

From 7/1/2019 to 7/31/2019

WO #:10484

Region: NER

Month Code: 10

Institution: NYM

Project #:

Approval: 7/18/2019

Title:2D3S Remove Asbestos
Expiration:7/18/2022

Funding

ng
Fiscal Year Funded: 2019
Percent Obligated: 0%
Allotted:$100,000.00
Obligated:$0.00
Unobligated:$100,000.00

Construction Status

Completion Percentage: 01%

Est. Completion: 7/18/2022

Progress Status: On Schedule

Completed:

Staff Man Hours

Total B&F ManHours:

Total S&E ManHours: 2.00

B&F ManHours this Month:

S&E ManHours this Month: 2.00

Estimated Hours: 600

Total S&E and B&F ManHours: 2.00

Detail Check List

☐ A&E Services required.

New construction will result in capitalization of a building or other structure.

Renovation will result in capitalization of an improvement to an existing building or other structure.

☑ Asbestos Abatement is required or has been completed.

☐ ESPC or UESC funded

□ FITARA process is required.

Funding

Fiscal Year Funded:2019
Percent Obligated:0%
Allotted:$120,320.00
Obligated:$0.00
Unobligated:$120,320.00

Construction Status

Completion Percentage: 01%

Est. Completion: 7/25/2022

Progress Status: On Schedule

Completed:

Staff Man Hours

Total B&F ManHours:

Total S&E ManHours: 1.00

Total S&E and B&F ManHours: 1.00

B&F ManHours this Month:
S&E ManHours this Month: 1.00
Estimated Hours:

Detail Check List

☐ A&E Services required.

New construction will result in capitalization of a building or other structure.

Renovation will result in capitalization of an improvement to an existing building or other structure.

☐ Asbestos Abatement is required or has been completed.

☐ ESPC or UESC funded

□ FITARA process is required.

Significant Project Events / Project Delays (Current Month Only)

2D3U Replace PBX - Project Approval Received 7/25/19. Procurement Documents Initiated.

AW:

Page 1 of 9

EFTA00142424

Federal Bureau of Prisons

MR 02 Monthly B&F Project Report

From 7/1/2019 to 7/31/2019

WO #:6633

Region: NER

Month Code: 10

Institution: NYM

Project #: 2C4G

Title: 2C4G Replace Doors Phase 2

Approval: 6/7/2017

Expiration: 6/7/2020

Funding

Fiscal Year Funded:2017
Percent Obligated:96.3219%
Allotted:$116,746.48
Obligated:$112,452.48
Unobligated:$4,294.00

Construction Status

Completion Percentage: 61%

Est. Completion: 6/7/2020

Progress Status: On Schedule

Completed:

Staff Man Hours

Total B&F ManHours:

Total S&E ManHours: 254.00

Total S&E and B&F ManHours: 254.00

B&F ManHours this Month:

S&E ManHours this Month: 1.00

Estimated Hours: 3,705

Detail Check List

☐ A&E Services required.

New construction will result in capitalization of a building or other structure.

☑ Renovation will result in capitalization of an improvement to an existing building or other structure.

☐ Asbestos Abatement is required or has been completed.

☐ ESPC or UESC funded

☐ FITARA process is required.

Significant Project Events / Project Delays (Current Month Only)

2C4G Replace Doors Housing Unit Phase II -

Number of Doors Installed This Month - 0

The Doors Were Installed On Unit -

Staff Hours Used This Month - 0

Cost of Materials Used This Month - $0

Number of Doors Left to Install On This Project - 14

Facility Manager:

AW:

Page 2 of 9

Bureau of Prisons monthly facilities project report for NYM, July 2019

Other records

Bureau of Prisons monthly building and facilities report for the NYM institution covering July 2019, detailing construction project funding, asbestos abatement, and door replacement progress

DOJ Epstein Files, Data Set 9 · July 2019

Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO :10484 Region: NER Month Code: 10 Institution: NYM Project : Approval: 7/18/2019 <table border="1" <tr <td Title:</td <td 2D3S Remove Asbestos</td </tr <tr <td Expiration:</td <td 7/18/2022</td </tr </table Funding <table <thead <tr <th ng</th </tr </thead <tbody <tr <td Fiscal Year Funded: 2019</td </tr <tr <td Percent Obligated: 0%</td </tr </tbody </table <table border="1" <tr <td Allotted:</td <td $100,000.00</td </tr <tr <td Obligated:</td <td $0.00</td </tr <tr <td Unobligated:</td <td $100,000.00</t…