# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:10484
Region: NER
Month Code: 10
Institution: NYM
Project #:
Approval: 7/18/2019
| Title: | 2D3S Remove Asbestos |
| Expiration: | 7/18/2022 |
Funding
| ng |
|---|
| Fiscal Year Funded: 2019 |
| Percent Obligated: 0% |
| Allotted: | $100,000.00 |
| Obligated: | $0.00 |
| Unobligated: | $100,000.00 |
# Construction Status
Completion Percentage: 01%
Est. Completion: 7/18/2022
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 2.00
B&F ManHours this Month:
S&E ManHours this Month: 2.00
Estimated Hours: 600
Total S&E and B&F ManHours: 2.00
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☑ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
□ FITARA process is required.
Funding
| Fiscal Year Funded: | 2019 |
| Percent Obligated: | 0% |
| Allotted: | $120,320.00 |
| Obligated: | $0.00 |
| Unobligated: | $120,320.00 |
# Construction Status
Completion Percentage: 01%
Est. Completion: 7/25/2022
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 1.00
Total S&E and B&F ManHours: 1.00
| B&F ManHours this Month: |
| S&E ManHours this Month: 1.00 |
| Estimated Hours: |
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
□ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3U Replace PBX - Project Approval Received 7/25/19. Procurement Documents Initiated.
AW:
Page 1 of 9
EFTA00142424
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:6633
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C4G
Title: 2C4G Replace Doors Phase 2
Approval: 6/7/2017
Expiration: 6/7/2020
Funding
| Fiscal Year Funded: | 2017 |
| Percent Obligated: | 96.3219% |
| Allotted: | $116,746.48 |
| Obligated: | $112,452.48 |
| Unobligated: | $4,294.00 |
# Construction Status
Completion Percentage: 61%
Est. Completion: 6/7/2020
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 254.00
Total S&E and B&F ManHours: 254.00
B&F ManHours this Month:
S&E ManHours this Month: 1.00
Estimated Hours: 3,705
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
☑ Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4G Replace Doors Housing Unit Phase II -
Number of Doors Installed This Month - 0
The Doors Were Installed On Unit -
Staff Hours Used This Month - 0
Cost of Materials Used This Month - $0
Number of Doors Left to Install On This Project - 14
Facility Manager:
AW:
Page 2 of 9