EFTA00142425
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:6926
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C4T
Title: 2C4T Repair Food Service Coolers
Approval: 7/29/2017
| Expiration: | 7/29/2020 |
| :--- | :--- |
Funding
| Fiscal Year Funded: | 2017 |
| Percent Obligated: | 72.772% |
| Allotted: | $15,200.00 |
| Obligated: | $11,061.35 |
| Unobligated: | $4,138.65 |
# Construction Status
Completion Percentage: 17%
Est. Completion: 7/29/2020
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 17.00
Total S&E and B&F ManHours: 17.00
| B&F ManHours this Month: |
| S&E ManHours this Month: 1.00 |
| Estimated Hours: 180 |
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C4T Repair Food Service Coolers -
Staff Hours Used This Month: 0
Tasks Completed This Month: Revised plan for placement of future condensate unit and how the lines will be run Tasks Left to Complete: Install Units. Run Lines
Plan Going Forward: Staff will mount units, then we will determine necessity for contractors
Facility Manager:
AW:
Page 3 of 9
EFTA00142426
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:7247
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C5N
Title: 2C5N Replace Food Service Trough
Approval: 10/23/2017
Funding
Expiration: 10/23/2020
| Fiscal Year Funded: | 2018 |
| Percent Obligated: | 40.233% |
| Allotted: | $12,000.00 |
| Obligated: | $4,827.97 |
| Unobligated: | $7,172.03 |
# Construction Status
Completion Percentage: 99%
Est. Completion: 10/23/2020
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 43.00
Total S&E and B&F ManHours: 43.00
B&F ManHours this Month:
S&E ManHours this Month: 0.50
Estimated Hours: 112
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
□ FITARA process is required.
## Significant Project Events / Project Delays (Current Month Only)
2C5N Replace Food Service Trough - All financial obligations have been met. Financial closure submitted. Awaiting NERO business office.
Facility Manager:
AW:
Page 4 of 9
EFTA00142427
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:8437
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C6Z
Title: 2C6Z MTA-Lead/Asbestos Removal MTA
Approval: 5/16/2018
| Expiration: | 5/16/2021 |
| :--- | :--- |
Funding
| Fiscal Year Funded: | 2018 |
| Percent Obligated: | 99.844% |
# Construction Status
Completion Percentage: 75%
Est. Completion: 5/16/2021
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 60.00
B&F ManHours this Month:
S&E ManHours this Month: 8.00
Estimated Hours: 2,400
Total S&E and B&F ManHours: 60.00
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
☑ Renovation will result in capitalization of an improvement to an existing building or other structure.
☑ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
## Significant Project Events / Project Delays (Current Month Only)
2C6Z MTA-Lead/Asbestos Removal MTA-
Type of Work Conducted This Month - Demolition: Removed 4 turbines, 1 tank, 1 switch
Staff Hours Used This Month - 8
Cost of Materials Used This Month - 0
Next Anticipated Work Type - Demolition: Remove Remaining Switches and Demo Turbines
Facility Manager:
AW:
Page 5 of 9
EFTA00142428
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:8282
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C8L
Title: 2C8L Replace Basement Elevator Saddle
Approval: 5/17/2018
Funding
Expiration: 5/17/2021
| Fiscal Year Funded: | 2018 |
| Percent Obligated: | 97.6091% |
| Allotted: | $45,000.00 |
| Obligated: | $43,924.10 |
| Unobligated: | $1,075.90 |
# Construction Status
Completion Percentage: 99%
Est. Completion: 5/17/2021
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 25.00
Total S&E and B&F ManHours: 25.00
| B&F ManHours this Month: |
| S&E ManHours this Month: 0.50 |
| Estimated Hours: 40 |
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
□ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8L Replace Basement Elevator Saddle-
Preparing documents for financial closure.
Facility Manager:
AW:
Page 6 of 9
EFTA00142429
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:8438
Region: NER
Month Code: 10
Institution: NYM
Project #: 2C8V
Title: 2C8V Repair Roof
Approval: 6/14/2018
Expiration: 6/14/2021
Funding
| Fiscal Year Funded: | 2018 |
| Percent Obligated: | 92.413% |
| Allotted: | $76,000.00 |
| Obligated: | $70,233.91 |
| Unobligated: | $5,766.09 |
# Construction Status
Completion Percentage: 99%
Est. Completion: 6/14/2021
| Progress Status: | On Schedule |
| Completed: | 8/13/2019 |
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 17.00
Total S&E and B&F ManHours: 17.00
| B&F ManHours this Month: |
| S&E ManHours this Month: 1.00 |
| Estimated Hours: 425 |
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2C8V Repair Roof- Project work completed, awaiting Financial Closure. Financial Closure submitted to Financial Management on 4/23/2019.
Facility Manager:
AW:
Page 7 of 9
EFTA00142430
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:9580
Region: NER
Month Code: 10
Institution: NYM
Project #: 2D2P
Title: 2D2P Emergency Replace Heating Coils
Approval: 2/8/2019
| Expiration: | 2/8/2022 |
| :--- | :--- |
Funding
| Fiscal Year Funded: | 2019 |
| Percent Obligated: | 24.1778% |
| Allotted: | $99,500.00 |
| Obligated: | $24,057.00 |
| Unobligated: | $75,443.00 |
# Construction Status
Completion Percentage: 66%
Est. Completion: 2/8/2022
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 102.00
B&F ManHours this Month:
S&E ManHours this Month: 2.00
Estimated Hours: 800
Total S&E and B&F ManHours: 102.00
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D2P Emergency Replace Heating Coils
Equipment Replaced This Month -
The Equipment Services -
Staff Hours Used This Month - 2
Cost of Materials Used This Month - $0
Equipment Left to Replace On This Project - Condensate Pumps, AHU Motors, In-Duct Coils
Next Anticipated Equipment Replacement Site Is - Condensate Pumps
Facility Manager:
AW:
Page 8 of 9
EFTA00142431
# Federal Bureau of Prisons
MR 02 Monthly B&F Project Report
From 7/1/2019 to 7/31/2019
WO #:10473
Region: NER
Month Code: 10
Institution: NYM
Project #: 2D3N
Title: 2D3N Construct Gun Locker
Approval: 7/17/2019
Funding
| Expiration: | 7/17/2022 |
| :--- | :--- |
| Fiscal Year Funded: | 2019 |
| Percent Obligated: | 0% |
| Allotted: | $200,000.00 |
| Obligated: | $0.00 |
| Unobligated: | $200,000.00 |
# Construction Status
Completion Percentage: 05%
Est. Completion: 7/17/2022
Progress Status: On Schedule
Completed:
# Staff Man Hours
Total B&F ManHours:
Total S&E ManHours: 8.00
Total S&E and B&F ManHours: 8.00
B&F ManHours this Month:
S&E ManHours this Month: 8.00
Estimated Hours: 1,920
Detail Check List
☐ A&E Services required.
New construction will result in capitalization of a building or other structure.
Renovation will result in capitalization of an improvement to an existing building or other structure.
☐ Asbestos Abatement is required or has been completed.
☐ ESPC or UESC funded
☐ FITARA process is required.
Significant Project Events / Project Delays (Current Month Only)
2D3N Construct Gun Lockers - Project Approval Received 7/17/19. RCA Packet prepared and sent for approval 7/26/19.
Facility Manager:
AW: