EFTA00142425 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:6926 Region: NER Month Code: 10 Institution: NYM Project #: 2C4T Title: 2C4T Repair Food Service Coolers Approval: 7/29/2017 | Expiration: | 7/29/2020 | | :--- | :--- | Funding
Fiscal Year Funded:2017
Percent Obligated:72.772%
Allotted:$15,200.00
Obligated:$11,061.35
Unobligated:$4,138.65
# Construction Status Completion Percentage: 17% Est. Completion: 7/29/2020 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 17.00 Total S&E and B&F ManHours: 17.00
B&F ManHours this Month:
S&E ManHours this Month: 1.00
Estimated Hours: 180
Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded ☐ FITARA process is required. Significant Project Events / Project Delays (Current Month Only) 2C4T Repair Food Service Coolers - Staff Hours Used This Month: 0 Tasks Completed This Month: Revised plan for placement of future condensate unit and how the lines will be run Tasks Left to Complete: Install Units. Run Lines Plan Going Forward: Staff will mount units, then we will determine necessity for contractors Facility Manager: AW: Page 3 of 9 EFTA00142426 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:7247 Region: NER Month Code: 10 Institution: NYM Project #: 2C5N Title: 2C5N Replace Food Service Trough Approval: 10/23/2017 Funding Expiration: 10/23/2020
Fiscal Year Funded:2018
Percent Obligated:40.233%
Allotted:$12,000.00
Obligated:$4,827.97
Unobligated:$7,172.03
# Construction Status Completion Percentage: 99% Est. Completion: 10/23/2020 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 43.00 Total S&E and B&F ManHours: 43.00 B&F ManHours this Month: S&E ManHours this Month: 0.50 Estimated Hours: 112 Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded □ FITARA process is required. ## Significant Project Events / Project Delays (Current Month Only) 2C5N Replace Food Service Trough - All financial obligations have been met. Financial closure submitted. Awaiting NERO business office. Facility Manager: AW: Page 4 of 9 EFTA00142427 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:8437 Region: NER Month Code: 10 Institution: NYM Project #: 2C6Z Title: 2C6Z MTA-Lead/Asbestos Removal MTA Approval: 5/16/2018 | Expiration: | 5/16/2021 | | :--- | :--- | Funding
Fiscal Year Funded:2018
Percent Obligated:99.844%
Allotted:$2,460,000.00
Obligated:$2,456,164.60
Unobligated:$3,835.40
# Construction Status Completion Percentage: 75% Est. Completion: 5/16/2021 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 60.00 B&F ManHours this Month: S&E ManHours this Month: 8.00 Estimated Hours: 2,400 Total S&E and B&F ManHours: 60.00 Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. ☑ Renovation will result in capitalization of an improvement to an existing building or other structure. ☑ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded ☐ FITARA process is required. ## Significant Project Events / Project Delays (Current Month Only) 2C6Z MTA-Lead/Asbestos Removal MTA- Type of Work Conducted This Month - Demolition: Removed 4 turbines, 1 tank, 1 switch Staff Hours Used This Month - 8 Cost of Materials Used This Month - 0 Next Anticipated Work Type - Demolition: Remove Remaining Switches and Demo Turbines Facility Manager: AW: Page 5 of 9 EFTA00142428 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:8282 Region: NER Month Code: 10 Institution: NYM Project #: 2C8L Title: 2C8L Replace Basement Elevator Saddle Approval: 5/17/2018 Funding Expiration: 5/17/2021
Fiscal Year Funded:2018
Percent Obligated:97.6091%
Allotted:$45,000.00
Obligated:$43,924.10
Unobligated:$1,075.90
# Construction Status Completion Percentage: 99% Est. Completion: 5/17/2021 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 25.00 Total S&E and B&F ManHours: 25.00
B&F ManHours this Month:
S&E ManHours this Month: 0.50
Estimated Hours: 40
Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded □ FITARA process is required. Significant Project Events / Project Delays (Current Month Only) 2C8L Replace Basement Elevator Saddle- Preparing documents for financial closure. Facility Manager: AW: Page 6 of 9 EFTA00142429 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:8438 Region: NER Month Code: 10 Institution: NYM Project #: 2C8V Title: 2C8V Repair Roof Approval: 6/14/2018 Expiration: 6/14/2021 Funding
Fiscal Year Funded:2018
Percent Obligated:92.413%
Allotted:$76,000.00
Obligated:$70,233.91
Unobligated:$5,766.09
# Construction Status Completion Percentage: 99% Est. Completion: 6/14/2021
Progress Status:On Schedule
Completed:8/13/2019
# Staff Man Hours Total B&F ManHours: Total S&E ManHours: 17.00 Total S&E and B&F ManHours: 17.00
B&F ManHours this Month:
S&E ManHours this Month: 1.00
Estimated Hours: 425
Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded ☐ FITARA process is required. Significant Project Events / Project Delays (Current Month Only) 2C8V Repair Roof- Project work completed, awaiting Financial Closure. Financial Closure submitted to Financial Management on 4/23/2019. Facility Manager: AW: Page 7 of 9 EFTA00142430 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:9580 Region: NER Month Code: 10 Institution: NYM Project #: 2D2P Title: 2D2P Emergency Replace Heating Coils Approval: 2/8/2019 | Expiration: | 2/8/2022 | | :--- | :--- | Funding
Fiscal Year Funded:2019
Percent Obligated:24.1778%
Allotted:$99,500.00
Obligated:$24,057.00
Unobligated:$75,443.00
# Construction Status Completion Percentage: 66% Est. Completion: 2/8/2022 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 102.00 B&F ManHours this Month: S&E ManHours this Month: 2.00 Estimated Hours: 800 Total S&E and B&F ManHours: 102.00 Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded ☐ FITARA process is required. Significant Project Events / Project Delays (Current Month Only) 2D2P Emergency Replace Heating Coils Equipment Replaced This Month - The Equipment Services - Staff Hours Used This Month - 2 Cost of Materials Used This Month - $0 Equipment Left to Replace On This Project - Condensate Pumps, AHU Motors, In-Duct Coils Next Anticipated Equipment Replacement Site Is - Condensate Pumps Facility Manager: AW: Page 8 of 9 EFTA00142431 # Federal Bureau of Prisons MR 02 Monthly B&F Project Report From 7/1/2019 to 7/31/2019 WO #:10473 Region: NER Month Code: 10 Institution: NYM Project #: 2D3N Title: 2D3N Construct Gun Locker Approval: 7/17/2019 Funding | Expiration: | 7/17/2022 | | :--- | :--- |
Fiscal Year Funded:2019
Percent Obligated:0%
Allotted:$200,000.00
Obligated:$0.00
Unobligated:$200,000.00
# Construction Status Completion Percentage: 05% Est. Completion: 7/17/2022 Progress Status: On Schedule Completed: # Staff Man Hours Total B&F ManHours: Total S&E ManHours: 8.00 Total S&E and B&F ManHours: 8.00 B&F ManHours this Month: S&E ManHours this Month: 8.00 Estimated Hours: 1,920 Detail Check List ☐ A&E Services required. New construction will result in capitalization of a building or other structure. Renovation will result in capitalization of an improvement to an existing building or other structure. ☐ Asbestos Abatement is required or has been completed. ☐ ESPC or UESC funded ☐ FITARA process is required. Significant Project Events / Project Delays (Current Month Only) 2D3N Construct Gun Lockers - Project Approval Received 7/17/19. RCA Packet prepared and sent for approval 7/26/19. Facility Manager: AW: Page 9 of 9 EFTA00142432